Eversource planning Gas Line replacement on Summer Street, Waltham Street & Powdermill Road

Beginning on or around August 11, 2025 and expected to continue for five (5) months, Eversource Gas will be actively replacing an aged existing gas line on sections of Summer Street, Waltham Street & Powdermill Road. (Please note: Dates are subject to change)

Most sections of the designated roads are not expected to be detoured, and one lane of alternating traffic will be maintained under Police Control at all times. If a temporary detour is required, it is expected during nighttime work operations when less traffic is expected on the roadways. Any Detours will be signed and maintained under Police Control at all times. 

The phases of the proposed work are listed below along with the approximate timeframe IN WEEKS for each phase: 

Phase 1 – Daytime Work between #48 and #43 Summer Street and at the Summer Street/Brooks/Maple Street intersection – Approximately 6 weeks 

Phase 2 – Daytime Work between #43 and #1 Summer Street – Approximately 4 weeks 

Phase 3 – Nighttime Work between #1 Summer Street and the Main Street Bridge near McDonalds – Approximately 3 weeks

Phase 4 – Nighttime Work between the Main Street Bridge near McDonalds and #1 Powdermill Road – Approximately 3 weeks 

Phase 5 – Daytime Work between #1 Powdermill Road and Douglas Avenue – Approximately 2 weeks 

If you have any questions, please contact the Maynard DPW at (978) 897-1317 or via email at [email protected].

Leave a Reply

Your email address will not be published. Required fields are marked *